Planning to Reconfigure the 150 kV Transmission Network at PT. PLN (Persero) Tualang Cut Network and Substation
Abstract
System condition at PT. PLN (Persero) Tualang Cut Substation where the reliability of the 150 kV system depends on the Langsa Substation, which we will reconfigure on the Lgs-P.B and Lgs-T.C channels to P.B-T. C and T.C-Lgs. The planning for the reconfiguration of the 150 kv transmission network of the Tualang Cut Substation was carried out by estimating the distance of the transmission line and the constraints that occurred. The condition of the electric power system that is currently operating at PT. PLN (Persero) Tualang Cut Substation is considered less efficient in receiving power from the 150 kV SUTT interconnection. The SUTT in Tualang Cut currently receives electrical power from the Langsa Substation with a Losses value on lines 1 and 2 of 771,4142474 kW and experiences a Voltage Drop on lines 1 and 2 of 4,38 kV. After we reconfigured the channel, from the results of the reconfiguration there was a decrease in Losses on channels 1 and 2 by 311,298581 kW which before the reconfiguration of power losses on the line amounted to 771,4142474 kW and after being reconfigured to 460,1156668 kW there was a decrease in Voltage Drop on channels 1 and 2 by 1,44 kV, before the reconfiguration of the voltage drop on the line of 4,38 kV and after the reconfiguration to 2,94 kV, the reconfiguration carried out is the best solution to reduce losses and voltage drops.
Keywords
Full Text:
PDFReferences
Aribowo, D., Desmira, Ekawati, R., & Jatnika, A. (2021). Analisa Sistem Elektrikal Pada Gedung Control Building Sudirman Central Business District Jakarta. Jurnal Inovasi Penelitian, 2(1), 59–68.
Arifin, S. (2017). Analisis Aliran Daya Pada Sistem Kelistrikan Sumatera Utara Menggunakan Software Powerword.
Arnawan, H., Muzamir, I., Mohd, I. Y., Siti, R. A. R., & Hadi, S. (2021). Evaluation Of 20 Kv Distribution Network Losses In Radial Distribution Systems Due To Distributed Generation Penetration. Journal Of Physics: Conference Series, 2129(1), 12085.
Azizurrohman, M., & Fadlun, W. (2019). Analisis Rugi-Rugi Daya Pada Saluran Transmisi Tegangan Tinggi 150 Kv Gardu Induk Batang – Gardu Induk Pekalongan Dengan Jenis Konduktor Accc Lisbon Naskah. 14.
Binilang, R. B., Tumaliang, H., Lisi, F., & Elektro-Ft, J. T. (2017). Studi Analisa Rugi Daya Pada Saluran Distribusi Primer 20 Kv Di Kota Tahuna. Jurnal Teknik Elektro Dan Komputer, 6(2), 69–78.
Catra Indra Cahyadi,Kurniaty Atmia, A. F. (2022). Analisis Pengaruh Rugi-Rugi Daya Pada Jaringan Transmisi 150 Kv Menggunakan Software Etap 12.6. 4, 8–12.
Hanung Yoba Abriyantoa, Fardhan Arkan, R. K. J. (2017). Analisa Rekonfigurasi Jaringan Sistem 20 Kv Bangka Untuk Meningkatkan Kualitas Pelayanan Pelanggan. 246–253.
Hasibuan, A., Badrina, B., & Hasibuan, A. Z. (2019). Simulasi Analisis Aliran Daya Sub Sistem Aceh 150 Kv Menggunakan Software Powerworld Simulator. Journal Of Electrical And System Control Engineering, 3(1), 42–52.
Hasibuan, A., Isa, M., Yusoff, M. I., & Rahim, S. R. A. (2020). Analisa Aliran Daya Pada Sistem Tenaga Listrik Dengan Metode Fast Decoupled Menggunakan Software Etap. Rele (Rekayasa Elektrikal Dan Energi): Jurnal Teknik Elektro, 3(1), 37–45.
Hasibuan, A., Kartika, K., Mahfudz, S., & Daud, M. (2022). Network Reconfiguration Of 20 Kv Sample Connection Substance Lg-04 Lhokseumawe City Using Digsilent Power Factory Software Simulation 15.1. International Journal Of Advances In Data And Information Systems, 3(1), 20–29.
Indah Permata Sari, Wahri Sunanda, A. (2017). Analisis Perencanaan Pembangunan Gardu Induk Dan Rekonfigurasi Jaringan 20 Kv Pada Pln Rayon Pangkalpinang. 7.
Ismail, R., Hasibuan, A., Nasution, E. S., Hardi, S., & Nrartha, I. M. A. (2020). Comparative Analysis Of Differential Relay Settings In Langsa Substation Transformer To Avoid Protection Failure. 2020 4rd International Conference On Electrical, Telecommunication And Computer Engineering (Elticom), 52–56.
Kartoni, J., & Ervianto, E. (2016). Analisa Rekonfigurasi Pembebanan Untuk Mengurangi Rugi-Rugi Daya Pada Saluran Distribusi 20 Kv. Jom Fteknik, 3(2), 1.
Listin, T. W., Thaha, S., & Naim, K. (2021). Anasisi Susut Energi (Losses) Jaringan Tegangan Menegah (20kv) Di Bandar Udara Internasional Sultan Hasanuddin Makassar. Seminar Nasional Teknik Elektro Dan Informatika (Sntei), September, 168–177.
M, F., Sukma, D. Y., & Ervianto, E. (2015). Analisis Keberadaan Dan Pengembangan Gardu Induk Distribusi 20 Kv Di Kota Pekanbaru. Jom Fteknik, 2(2), 1–15.
Musdir, N. A., Arief, A., & Nappu, M. B. (2022). Penempatan Distributed Generation Optimal Mempertimbangkan Rekonfigurasi Jaringan. Jurnal Eksitasi, 1(2), 2022.
Nasution, E. S. (2019). Analisis Rugi-Rugi Daya Pada Saluran Transmisi Tegangan Tinggi 150 Kv Rantauprapat-Padang Sidempuan. Kumpulan Jurnal Dosen Universitas Muhammadiyah Sumatera Utara, 5(2).
Putranti, R. D., & Setiono, I. (2014). Perhitungan Kerugian Energi Pada Penyulang Tambak Lorok-03 Sebagai Salah Satu Pilot Project Program Revass (Revenue Assurance) Dalam Program Rekonsiliasi Energi Pt. Pln (Persero) Area Semarang. Gema Teknologi, 18(1), 16. Https://Doi.Org/10.14710/Gt.V18i1.8810
Rahmadhani, S. N. (2018). Evaluasi Efektivitas Pengendalian Internal Pada Jaringan Distribusi Di Sistem 20 Kv (Kilo Volt) Studi Kasus: Pt Pln (Persero) Wilayah Sumatera Utara. Jurnal Akuntansi Dan Bisnis : Jurnal Program Studi Akuntansi, 4(2), 24. Https://Doi.Org/10.31289/Jab.V4i2.1816
Rajagukguk, A. S. F., Pakiding, M., & Rumbayan, M. (2015). Kajian Perencanaan Kebutuhan Dan Pemenuhan Energi Listrik Di Kota Manado. Jurnal Teknik Elektro Dan Komputer, 4(3), 1–11.
Saputra, M. L. (2019). Rekonfigurasi Jaringan Distribusi Pada Penyulang Gl. 01 Sebagai Upaya Penekanan Losses Menggunakan Software Etap 12.6. 0. Jurnal Energi Elektrik, 8(1), 18–24.
Syukri, S., Asyadi, T. M., Muliadi, M., & Moesnadi, F. (2022). Analisa Pembebanan Transformator Distribusi 20 Kv Pada Penyulang Ls5 Gardu Lsa 249. Jambura Journal Of Electrical And Electronics Engineering, 4(2), 202–206. Https://Doi.Org/10.37905/Jjeee.V4i2.14500
Talaat, M., El-Shaarawy, Z., Tayseer, M., & El-Zein, A. (2021). An Economic Study Concerning The Cost Reduction Of The Covered Transmission Conductors Based On Different Optimization Techniques. Results In Engineering, 11(August), 100262. Https://Doi.Org/10.1016/J.Rineng.2021.100262
Tanjung, A. (2014). Rekonfigurasi Sistem Distribusi 20 Kv Gardu Induk Teluk Lembu Dan Pltmg Langgam Power Untuk Mengurangi Rugi Daya Dan Drop Tegangan. 11(2), 160–166.
Tenda, N., Lily S. Patras, S. M., & Ir. Hans Tumailang, M. (2016). Penyusutan Daya Listrik Pada Penyulang Jaringan Transmisi Isimu Marisa. E-Journal Teknik Elektro Dan Komputer, 5(1), 2301–8402.
Utomo, S. B., & Haddin, M. (2019). Analisis Perhitungan Rugi-Rugi Daya Pada Saluran Transmisi Tegangan Tinggi 150 Kv Gardu Induk Tambak Lorok – Bawen Dengan Menggunakan Etap 12.6.0. 234–243.
Wantouw, F., & Mandagi, R. J. M. (2014). Manajemen Resiko Proyek Pembangunan Saluran Udara Tegangan Tinggi (Sutt) 150 Kv Lopana - Teling. Jurnal Ilmiah Media Engineering, 4(4), 239–256.
DOI: https://doi.org/10.29103/jreece.v3i2.11740
Article Metrics
Abstract Views : 189 timesPDF Downloaded : 60 times
Refbacks
- There are currently no refbacks.
Copyright (c) 2023 Arnawan Hasibuan, Asran, Fery Adriansyah, Baharuddin Ismail, Widyana Verawaty Siregar, Muhammad Sayuti
This work is licensed under a Creative Commons Attribution-ShareAlike 4.0 International License.